Project Description
Darquain Oil Field Development 2nd Stage
In the second stage of development, fifteen production wells will be added to the previous eight. To maintain reservoir pressure, four gas injection wells and one water injection well will be utilized.
Expected Production Capacity:
- Second Stage: 130,000 barrels of oil per day (BOPD)
- First Stage: 50,000 BOPD
- Total Capacity: 180,000 BOPD
Major Surface Facilities
I. Gathering and Injection System (Off-Plot Area):
- Wellhead Area
- Cluster Area: Manifolding wellhead production
- Production Lines: 6”, 10”, 12”
- Injection Lines: 10”, 12”
II. Oil Treatment and Gas Compression (On-Plot Area):
- Oil Production (Treatment) Trains:
- Two trains (one existing from the first stage)
- Gas Compression Trains:
- Three trains (2-stage compressor) (one added in the first stage)
- Utility Area
- Substations:
- One 33/6 KV substation
- One 6/0.4 KV substation