Project Description
Bibi-Hakimeh New Gas Compressor Station
Client
Persian Gulf Bidboland Gas Treating (PGBGT)
Owner
National Iranian South Oilfields Company (NISOC)
Location
Bibi-Hakimeh, Bushehr Province, Iran
The Bibi-Hakimeh Gas Compressor station is located in Iran’s Bushehr Province, approximately 30 kilometers from Deilam port. This project is essential for supplying feed to the Persian Gulf Bid Boland Refinery.
Key Objectives
- Change of Injection Gas Source: Transition from gas produced by NGL 1300 to South Pars Gas (6th, 7th, 8th phases).
- Utilization of Acid Gas: Use acid gas produced by the NGL 1300 plant for the Bibi-Hakimeh oil wells.
Project Background
- Initial Design: The initial engineering design was carried out by another company.
- Delays in Procurement: Due to delays in the procurement of compressors, the client decided to relocate and use two turbo compressor trains from the Gachsaran New Gas Compressor Station at the Bibi-Hakimeh New Gas Compressor Station.
Project Scope
- Impact Study: Assess the impact of this change on the previous Front-End Engineering Design (FEED).
- Documentation: Prepare new documentation reflecting these changes.
- EPCC Tender Document: Develop an Engineering, Procurement, Construction, and Commissioning (EPCC) tender document.
Contract Time Period
- Duration: September 2019 to October 2019.