Gas Inlet Line from Sea line to Onshore Facilities

Petro Tadbir e Pars Company as Contractor of Persian Oil & Gas Company (Owner) intends to connect phase 18 sea line gas field to phase 15 for production at full capacity by approximately 2 Km 32” pipeline. The purpose of this project is using full production capacity of phase 15&16 onshore facilities until the fully commissioning of phase 15&16 offshore facilities. This project has been awarded to Tehran Raymand for conceptual, detail design, and field engineering activities.

Contract Time Period:

August 2014 ~ November 2014

Services:

  • Conceptual Study
  • Detail Engineering
  • Field Engineering Activities
Assaluyeh Map Location
Assaluyeh, Iran

Client

Petro Tadbire Pars Company

Owner

Persian Oil & Gas Company (POGC)