Persian Gulf Bid Boland Gas Refinery is currently designed to receive 2000 MMSCFD feed gas including 1700MMSCFD sour gas from NGLs 900 & 1000 and 300 MMSCFD sweet gas from NGLs 1200 & 1300. Regarding the dependency of the feeds’ availability to the projects defined upstream of NGLs 900 & 1000 and gathering of the associated gas streams upstream of NGLs 1200, 1300 & 1500, CLIENT tends to perform Basic Design & FEED on these areas. The project goal is to ensure the gathering and treatment of the existing flared gas streams and transferring them to Persian Gulf Bid Boland Gas Refinery.
The scope of the project could be split into two main categories of study:
- Handling of the produced associated gas in the fields of Aghajari, Ramshir, RagSefid-1 and Sour Marun Asmari (Marun-3 & Marun-5) and Pazanan-1. The total gas quantity is higher than 400 MMSCFD and the majority is being flared due to absence of gas gathering and transmission system or wear and tear of the existing facilities that makes them practically unusable.
- Gas gathering and transmission systems in the fields upstream of NGLs 1200, 1300 & 1500. The major fields are Gachsaran, Bibihamikeh, Karanj, Paranj, Parsi, RagSefid-2 and the existing facilities in RagSefid-1. The gas gathering systems are currently in service and could remain in service for some extra years if the already defined repairing/improvement projects will be performed.
Contract Time Period:
May 2019 ~ May 2020
Services:
- Basic Design & FEED Preparation
- Procurement Services for Long Lead Items