The National Iranian Oil Engineering and Construction Company (NIOEC) initiated the Esfahan Refinery Upgrading Project to address de-bottlenecking and upgrading needs at the Esfahan Refinery. The project’s ultimate objectives are to reduce or minimize fuel oil production, increase gasoline production, and upgrade the refinery’s products to meet international standards. These objectives will be achieved through the installation of new units and the de-bottlenecking/revamping of existing units.
To achieve these goals, the project has been divided into five separate sub-projects and contracts:
Contract C, awarded to Tehran Raymand Consulting Engineers, is primarily responsible for supplying and distributing the required utilities for the OSBL (Outside Battery Limits) process units, designing the flare system and gathering networks, and interconnecting process and utility piping. This involves the following engineering activities:
A. Basic and Detailed Process Design:
B. Endorsement, Development, and Detailed Design:
C. Interface Management
D. Field Engineering Services