NGL-2300 and CFU-200
A) NGL-2300 (Ahwaz) The purpose of NGL-2300 plant is to maximize the C2+ recovery. The feed gas for this plant is provided from: Separated gas from 1st stage of Maroon-Khami plant (156 MMSCFD) Gas condensate stabilization units of Maroon-Khami plant (18 MMSCFD) Produced gas…
View all projectsProject brief
- Client
- National Iranian South Oil Company (NISOC)
- Location
- Ahwaz / Bandar Mahshahr, Iran
- Contract period
- Oct-2006 ~ Sep-2010
- Services
-
- Feasibility Study
- Basic Engineering
- Value Engineering
- FEED Package Preparation
- Preparation of Tender Package for EPCC Project
Project overview
A) NGL-2300 (Ahwaz) The purpose of NGL-2300 plant is to maximize the C2+ recovery. The feed gas for this plant is provided from: Separated gas from 1st stage of Maroon-Khami plant (156 MMSCFD) Gas condensate stabilization units of Maroon-Khami plant (18 MMSCFD) Produced gas from Maroon-5 production unit (82 MMSCFD) Recovered C2+ condensates in this plant are transferred to CFU-200 separation unit in Mahshahr and produced sweet gas is injected to Maroon oil field.
This plant consists of following units: LP gas compression unit Gas sweetening unit Gas dehydration unit Acid gas compression unit C2+ recovery unit C2+ purification unit Utilities Pipelines (C2+ condensates, Sweet Gas and Acid Gas) B) CFU-200 C2+ Separation plant (Bandar Maah-Shahr) C2+ from NGL 2300 (Above), NGL 1700, 1900 & 2000 is gathered in CFU-200 plant. In this plant Ethane, Propane, Butane and C5+ will be recovered and stored/transferred.
This plant includes below units: De-Ethanizer De-Propanizer De-Butanizer Storage Tanks (for Propane, Butane and C5+) Transfer Pumps Utilities
Project location
Ahwaz / Bandar Mahshahr, Iran