Project Description
Preliminary Front End Engineering Design (Pre-FEED) and Front End Engineering Design (FEED) works Cheshmeh-Khosh, Dalpari and East Paydar Oil Fields
Client
ZN-Vostok Company
Owner
ZN-Vostok Company (PEDEC as the main owner)
Location
West of Dezful, Iran
The Cheshmeh-Khosh, Dalpari, and East Paydar oil fields are located in the western part of Iran’s Ilam province, near the Iran-Iraq border. In October 2018, the National Iranian Oil Company (NIOC) signed a Development and Production Operations Service Contract (IPC) with ZN Vostok Ltd to enhance these fields.
The project involves:
- Conducting Engineering Surveys
- Developing Preliminary Front-End Engineering Design Documentation
- Developing Front-End Engineering Design Documentation
Key components of the project include:
- Wellhead Facilities
- Well Flow Lines, Manifolds, and Gathering Systems
- Automated Group Metering Unit (AGMU)
- Separation Facilities
- Desalting Unit
- Wastewater Treatment Unit
- Water Intake System
- Water Injection Pumps
- Oil Storage Facilities
- Reconstruction of the Drainage System
- Reconstruction of the Firefighting Station
- Reconstruction of the Chemical Analysis Laboratory
- 220/33 kV Power Station
- Power and Overhead Lines
The contract period spans from May 2021 to October 2024.