During this stage, three appraisal wells, five development wells, and one gas injection well are supposed to be drilled. The expected oil production is 50,000 BOPD.
The surface facilities will be comprised of:
- Gathering system.
- A production facility with a sustainable oil treatment capacity (design condition) of 55,000 (peak rate 60,000) BOPD.
- A 17 Km 12” export oil pipeline to a tie-in point beyond the Karun river
- Gas injection system to recover the gas production coming from the 1st and 2nd stages oil separators, with a gas compression capacity of 70 MMSCFD
Contract Time Period:
June 2002 to March 2005
Cooperation With Other Companies:
- Sazeh Consultant Co.
- Snamprogetti Ltd.
Services:
- Detail engineering
- Procurement engineering services for local and foreign supplied equipment & material