FARZANEGAN ENERGY PARS Co. as EMPLOYER has planned to build FARZANEGAN gas condensate refinery, with design capacity of 40,000 BPSD on the Iranian coast of the Persian Gulf in the area of Assaluyeh (approximately 270 km South East of Bandar Bushehr).
The services include:
- Detailed engineering services
- Procurement engineering services
- Site engineering services
The main units of this project are listed here:
- Unit 01: Gas Condensate Pre Fractionation Unit (GCFU)
- Unit 02: Full Range Naphtha Hydrotreating Unit (NHT)
- Unit 03: Solvent Production Unit
- Unit 09: Sulfur Recovery Unit
- Unit 20: off-site unit (including tankage and product transfer pumps)
- Unit 30: Product Truck Loading Station (including loading/unloading facilities)
- Unit 50: Pipeline
- Unit 07: Hydrogen Production Unit
- Unit 21: Steam and Condensate Unit
- Unit 22: Water System Unit (Including Cooling Water Package, Plant and Potable Water Package and Demin water Package)
- Unit 23: Fuel Oil and Fuel Gas
- Unit 24: Plant and Instrument Air
- Unit 11: Nitrogen Production System
- Unit 25: Flare Unit
- Unit 26: Waste Water Treatment Unit
- Unit 32: Fire Water Unit
- Unit 45: Interconnection
- Industrial Buildings
- Non-Industrial Buildings
Contract Time Period:
March 2024 ~ September 2026
Services:
- Detailed Design Engineering
- Licensor Proposals Review and evaluate
- Procurement Services (Bidders Proposal Review, TBE & VDR)