The project comprises of a grass root natural gas treatment plant to be built west of Turkmenistan. The plant design capacity is 26 MMSCM of sales gas and extraction of 2600 SCM of stabilized condensate is envisaged to be used inside Turkmenistan. Both sales gas and condensate will be delivered at the plant battery limits.
In addition, two metering stations for custody transfer of natural gas, comprising 4 meter runs (3 operating and one spare) with 9 MMSCM/D capacity per each meter run, is also included in this project.
Tehran Raymand was in charge of performing basic and detail engineering of Buildings and Auxiliary Facilities of plant.